Skip to main content

Public contracts of Pluvigner · 2022 · Construction and buildings

Réaménagement du centre-ville

€103k
contract ceiling — what was paid on it is not published
Signed on 2 September 2022 · ended around September 2024 · 2 yrs

Who won it

Okare IngenierieIngénierie, études techniques · registered office Cesson-Sevigne (35510) · headcount 20 to 49 employees · SIREN 511617029

Main holder, with the largest amount. The contract has 3 holders; the others are not shown here yet.

The largest of the 2 contracts Pluvigner published for 2022.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.