Mo pr rehabiliotation thermique bâtiment s LYC v.LABBE a la madeleine

€67k
maximum contract amount over 4 years — what was paid on it is not published
Signed on 18 August 2026 · running until about August 2030 · 4 yrs
Ongoing18 Aug 2030

That is at most ~€17k a year on average: a maximum too.

Company selected

Ba BatIngénierie, études techniques · registered office Ruitz (62620) · headcount 20 to 49 employees · SIREN 428562649

A contract awarded to a consortium of 3 holders; above, the main holder. With it: Polynome Architectes, Exeo Ingenierie. The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 72 by amount of the 84 contracts the Hauts-de-France region published for 2026.

Other contracts of Ba Bat in Hauts-de-France

Ms 2 mo pour TRAVX de restructuration 1ère phase LYC d’aumont a COUCY…2026 · maximum over 3.5 years72€kMo pour réhab thermique bâtiment a et b au LYC kernanec marcq en baroeul2025 · maximum over 3 years217€kMission mo réhabilitation lourde bâtiment i lp cousteau wasquehal2023 · maximum over 4.5 years166€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.