Mandat de maîtrise d’ouvrage relatif à la rénovation globale du lycée Jean-Pierre Vernant à Sevres

€962k
maximum contract amount over 8 years — what was paid on it is not published
Signed on 1 June 2026 · running until about June 2034 · 8 yrs
Ongoing1 Jun 2034

That is at most ~€120k a year on average: a maximum too.

Company selected

Oteis PartnersSIREN 951804624

The competition

2 bids received

Median for this procedure in 2026: 1 bid, across 1931 comparable contracts. Contract awarded without prior advertising or competitive bidding · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 56 by amount of the 339 contracts the Île-de-France region published for 2026.

Other contracts of Oteis Partners in Île-de-France

Mandat de maîtrise d’ouvrage relatif à l’opération de reconstruction…2025 · maximum over 6.5 years470€k
Contract details (procedure, price, amendments, lots)

Procedure : Marché passé sans publicité ni mise en concurrence préalable

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Mandat de maîtrise d’ouvrage relatif à la rénovation globale du lycée…: up to €962k over 8 years, Île-de-France 2026 · Qipu