Public contracts of Rezé · 2020

Numéro de la consultation : 2019TX0061 Extension en modulaire de l’école maternelle Château Sud

Number 17 by amount of the 67 contracts Rezé awarded in 2020.

Contract · Construction and Bâtiment · carried out in 44400

136k €
contract ceiling — what was paid on it is not published
Signed on 22 May 2020 · ended around November 2020 · 0.5 yrs
Ended21 Nov 2020

Who won it

EgdcSIREN 626520126

The competition

Number of bids not published for that year: the field is only systematic from 2024.

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceRévisable
Published amendmentsnone

Other contracts of Egdc in Rezé

Travaux de Restructuration d’un bâtiment en lieu dédié à la prévention et à la tranquillité2026256k€Travaux d’extension et restructuration de l’école élémentaire Simone Veil (La Houssais)2021308k€Extension du restaurant scolaire et rénovation des façades de l’école élémentaire Chêne Creux (relance suite consultation infructueuse)2021275k€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.