Construction du groupe scolaire du secteur Est

€173k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 4 December 2018 · ended around June 2020 · 18 months

That is at most ~€115k a year on average: a maximum too.

Company selected

Asc RobineTravaux de menuiserie métallique et serrurerie · registered office Brehal (50290) · headcount 20 to 49 employees · SIREN 325763894

Number 2 by amount of the 3 contracts Saint-Lô published for 2018. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : 2

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.