Skip to main content

Public contracts of Saint-Mitre-les-Remparts · 2019 · Construction and buildings

Travaux divers à l’école élémentaire Edouard Vaillant

€48k
maximum contract amount over 2 months — what was paid on it is not published
Signed on 2 July 2019 · ended around September 2019 · 2 months

Company selected

Gouiran et FilsTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Martigues (13500) · headcount 6 to 9 employees · SIREN 508042520

Number 7 by amount of the 19 contracts Saint-Mitre-les-Remparts published for 2019. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.