Chauffage

€83k
maximum contract amount over 7 months — what was paid on it is not published
Signed on 18 June 2024 · ended around January 2025 · 7 months

Company selected

Trullen BâtimentTravaux d'installation d'équipements thermiques et de climatisation · registered office Le Grand-Bourg (23240) · headcount 20 to 49 employees · SIREN 490769718

The largest of the 3 contracts Saint-Priest-la-Feuille published for 2024.

Other contracts of Trullen Bâtiment in Saint-Priest-la-Feuille

Chauffage, ventilation et plomberie sanitaire2023 · maximum over 9 months56€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Unitaire

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.