Public contracts of Saint-Priest-la-Feuille · 2023 · Construction and buildings

Chauffage, ventilation et plomberie sanitaire

€56k
maximum contract amount over 9 months — what was paid on it is not published
Signed on 8 December 2023 · ended around September 2024 · 9 months

Company selected

Trullen BâtimentTravaux d'installation d'équipements thermiques et de climatisation · registered office Le Grand-Bourg (23240) · headcount 20 to 49 employees · SIREN 490769718

Number 3 by amount of the 3 contracts Saint-Priest-la-Feuille published for 2023.

Other contracts of Trullen Bâtiment in Saint-Priest-la-Feuille

Chauffage2024 · maximum over 7 months83€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.