Skip to main content

Public contracts of Saint-Rémy · 2022 · Construction and buildings

Construction Hall couverte

€62k
contract ceiling — what was paid on it is not published
Signed on 29 March 2022 · ended around March 2023 · 12 months

Who won it

TexabriFabrication de structures métalliques et de parties de structures · registered office Reventin-Vaugris (38121) · headcount 20 to 49 employees · SIREN 378079065

The largest of the 3 contracts Saint-Rémy published for 2022.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Construction Hall couverte: €62k, Saint-Rémy 2022 · Qipu