Skip to main content

Public contracts of Saint-Sébastien-sur-Loire · 2019 · Energy

Travaux de réfection et réaménagement du manoir de la Tullaye

Électricité

€8k
maximum contract amount over 6 months — what was paid on it is not published
Signed on 23 July 2019 · ended around January 2020 · 6 months

Company selected

Ceco ElecTravaux d'installation électrique dans tous locaux · registered office Reze (44400) · headcount 1 or 2 employees · SIREN 412662314

Number 36 by amount of the 38 contracts Saint-Sébastien-sur-Loire published for 2019.

Other contracts of Ceco Elec in Saint-Sébastien-sur-Loire

Travaux pour l’extension de l’école maternelle du centre2021 · maximum over 2 years96€kConstruction de locaux de stockage associatifs2020 · maximum over 10 months2€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.