Public contracts of Sainte-Marie · 2025 · Construction and buildings

Démolition

€56k
contract ceiling — what was paid on it is not published
Signed on 18 July 2025 · ended around August 2025 · 1 month

Who won it

CubeConstruction d'autres bâtiments · registered office Ducos (97224) · SIREN 789380110

Number 14 by amount of the 17 contracts Sainte-Marie published for 2025.

Other contracts of Cube in Sainte-Marie

Gros œuvre202561€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Démolition: €56k, Sainte-Marie 2025 · Qipu