Skip to main content

Public contracts of Selongey · 2025 · Construction and buildings

Rénovation quillier

€44k
contract ceiling — what was paid on it is not published
Signed on 30 June 2025 · ended around January 2026 · 7 months

Who won it

SARL Styl'-Renov'Travaux de maçonnerie générale et gros œuvre de bâtiment · registered office Le Montsaugeonnais (52190) · headcount 10 to 19 employees · SIREN 451969794

Number 7 by amount of the 8 contracts Selongey published for 2025.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : 2

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.