Public contracts of Strasbourg · 2025 · Other

Travaux requalification avenue schutzenberger et aménagement chemin du wacken a Strasbourg

€286k
maximum contract amount over 21 months — what was paid on it is not published
Signed on 7 May 2025 · running until about February 2027 · 21 months
Ongoing5 Feb 2027

That is at most ~€163k a year on average: a maximum too.

Company selected

PontiggiaConstruction de routes et autoroutes · registered office Horbourg-Wihr (68180) · headcount 200 to 249 employees · SIREN 380722504

The competition

5 bids received

Median for this procedure in 2025: 3 bids, across 49692 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 119 by amount of the 569 contracts Strasbourg published for 2025. It belongs to the policy Streets and transport.

Other contracts of Pontiggia in Strasbourg

Travaux d’aménagement des espaces publics du secteur Lyautey2026 · maximum over 4 years800€kAménagement d’une air de jeux sur les espaces publics de la phase 1 à…2026 · maximum over 12 months197€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Clause sociale

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.