Skip to main content

Public contracts of Thionville · 2024 · Construction and buildings

Travaux de rénovation énergétique de l’École maternelle des Basses Terres

Peinture

€24k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 5 December 2024 · ended around December 2025 · 12 months

Company selected

Al Renov' Entreprise Générale de PeintureTravaux de peinture et vitrerie · registered office Metz (57070) · headcount 6 to 9 employees · SIREN 848934501

The competition

4 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 48 by amount of the 54 contracts Thionville published for 2024. It belongs to the policy Schools.

Other contracts of Al Renov' Entreprise Générale de Peinture in Thionville

Travaux de rénovation énergétique des vestiaires du complexe omnisport…2024 · maximum over 2 months7€kRestructuration de la salle communale de Garche2020 · maximum over 10 months21€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.