Public contracts of Thue et Mue · 2023 · Energy

Points de comptage et d’estimation gaz

€60k
framework agreement: a maximum envelope for orders over 2 years, not spending — what was paid on it is not published
Signed on 7 July 2023 · ended around July 2025 · 2 yrs

That is at most ~€30k a year on average: a maximum too.

Company selected

Totalenergies Électricité et Gaz FranceCommerce d'électricité · registered office Paris (75015) · headcount 500 to 999 employees · SIREN 442395448

Amounts paid

Electricity, gas and heating: €101k paid by Thue et Mue in 2023, all suppliers together (its accounts). The accounts do not say what share went to Totalenergies Électricité et Gaz France.

Number 3 by amount of the 3 contracts Thue et Mue published for 2023.

Other contracts of Totalenergies Électricité et Gaz France in Thue et Mue

Électricité (36 kVA)2024 · maximum over 2 years420€kÉlectricité pour les points de livraison raccordés en basse tension (36…2024 · maximum over 12 months316€kÉlectricité, puissance supérieure ou égale à 36 kVA : marché subséquent…2024 · maximum over 2 years156€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.