Public contracts of Tourcoing · 2024 · Construction and buildings
Centre social des Trois Quartiers
Construction d’une extension, réhabilitation et démolition d’une partie de l’existant: · Sols dures · Faïence
That is at most ~€20k a year on average: a maximum too.
Company selected
SAS DecottegnieTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Bondues (59910) · headcount 20 to 49 employees · SIREN 885580035The competition
Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company
Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.
Number 48 by amount of the 72 contracts Tourcoing published for 2024. It belongs to the policy Health and social care.
Other contracts of SAS Decottegnie in Tourcoing
Construction de vestiaires sportifs et d’un club-house au Stade du…2025 · maximum over 9 months255€kCentre social des Trois Quartiers, extension : démolition, voirie…2024 · maximum over 14 months617€kGros œuvre, carrelage, plâtrerie et clôtures béton dans écoles…2023 · maximum over 4 years3.2€MContract details (procedure, price, amendments, lots)
Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds
Price : Forfaitaire
Published amendments : none
Subcontracting declared : no