Public contracts of Tourcoing · 2025
Construction de vestiaires sportifs et d’un club-house au Stade du Tilleul et démolition de l’existant.: Lot 1: Démolition - Gros oeuvre étendu
Number 21 by amount of the 55 contracts Tourcoing awarded in 2025.
Original label (DECP) : « Construction de vestiaires sportifs et d’un club-house au Stade du Tilleul et démolition de l’existant.: Lot 1: Démolition - Gros oeuvre étendu » · Contract · Construction and Bâtiment · Travaux · carried out in 59200 · social clauses · environmental clauses
255k €
contract ceiling — what was paid on it is not published
Who won it
SAS DecottegnieSIREN 885580035The competition
2 bids received
Adapted procedure · awarded to 1 company
Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.
The form of the contract
PriceForfaitaire
Published amendmentsnone
Subcontracting declaredno
Social considerationsClause sociale
Environmental considerationsClause environnementale
Other contracts of SAS Decottegnie in Tourcoing
Centre social des Trois Quartiers - Construction d’une extension, réhabilitation et démolition d’une partie de l’existant: Lot 1: Démolition - VRD - Gros oeuvre2024617k€Centre social des Trois Quartiers - Construction d’une extension, réhabilitation et démolition d’une partie de l’existant: Lot 11: Sols dures - Faïence202424k€Gros oeuvre, Carrelage, Revêtement mural scellé, Plâtrerie, Clôture béton dans les écoles et les équipements sportifs20233.2M€Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.