Skip to main content

Public contracts of Villefranche-sur-Saône · 2019 · Construction and buildings

Restructuration bâtiment ancien école jean zay

€68k
maximum contract amount over 10 months — what was paid on it is not published
Signed on 17 July 2019 · ended around May 2020 · 10 months

Company selected

SM Bertholon ÉlectricitéTravaux d'installation électrique dans tous locaux · registered office Vindry-Sur-Turdine (69490) · headcount 6 to 9 employees · SIREN 305834459

Number 33 by amount of the 44 contracts Villefranche-sur-Saône published for 2019. It belongs to the policy Schools.

Other contracts of SM Bertholon Électricité in Villefranche-sur-Saône

Électricité courants forts et faibles2025 · maximum over 17 months202€kÉlectricité cfa2023 · maximum over 11 months78€kRénovation et mise en accessibilité de la halle bointon2023 · maximum over 11 months78€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.