Public contracts of Villeneuve-Tolosane · 2024 · Construction and buildings

Ossature bois

Charpente · Couverture · Zinguerie · Terrasse bois

€100k
maximum contract amount over 16 months — what was paid on it is not published
Signed on 12 March 2024 · ended around July 2025 · 16 months

That is at most ~€75k a year on average: a maximum too.

Company selected

Eco et Avenir BoisTravaux de charpente · registered office Carbonne (31390) · headcount 10 to 19 employees · SIREN 807655295

The competition

1 bid received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 35 by amount of the 63 contracts Villeneuve-Tolosane published for 2024.

Other contracts of Eco et Avenir Bois in Villeneuve-Tolosane

Charpente / couverture / bardage2026 · maximum over 6 months67€kTravaux de création du Centre Social à la Maison pour tous2026 · maximum over 5 months67€kRénovation de la Maison Leyrisse2024 · maximum over 11 months107€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 6

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.