New Headworks FCTY CM Services

H D R ENGINEERING INC · PUC Public Utilities Commsn

San Francisco agreed $24.9M with H D R ENGINEERING INC for contract 1000000335 (PUC Public Utilities Commsn); $34.2M has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.

Register title:PUC NEW HEADWORKS FCTY CM SRVS

Signed by Public Utilities Commsn

Agreed
$24.9M
Paid
$34.2M
more than the recorded base
Remaining (calculated)
$0
The money
Paid against the agreed amount

$34.2M paid · $9.3M more than the recorded base amount · Agreed $24.9M

Payments per fiscal year
1920212223242526
Largest year: $10.4M · dashed = fiscal year not closed yet

These bars total $31.4M; the figure above is $34.2M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.

Payment detail begins FY2018
The deal
Contract term
June 15, 2017December 14, 2025
Term ended
Recorded purchasing authority
Purchasing authority, verbatim
TERM CONTRACT PROFSERV-BID, ENVIRONMENTAL CONSULTING

See every contract awarded under Competitive bid →

Project team
SupplierRoleAttached $
H D R ENGINEERING INCPrime
JOE HILL CONSULTING ENGINEERSLBESubcontractor$3.3M
C M PROSLBESubcontractor$2.0M
SAYLOR CONSULTING GROUPLBESubcontractor$1.1M
APEX TESTING LABORATORIES INCLBESubcontractor$366,999
THE LABOR COMPLIANCE MANAGERS (TLCM)Subcontractor$27,938

Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.

Sources
This contract in the source
Raw rows (JSON, data.sfgov.org)