Skip to main content

Public Utilities Commission

Alameda Creek diversion restoration

Original title: “PUC Alameda Creek Divsn Restrn”

$116,957
paid on this contract in FY2025
$480,625 paid so far, of $600,000 agreed · runs to April 2027
April 27, 2023April 26, 2027
running

Paid to

HDR Engineering Incprime contractor$480,625

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Water fund100%$116,957

Paid year by year, FY2024–FY2026

$244,468 in FY2024 · $55,799 in FY2026

Click a year to see its amount.

Type and award

Contract type: Professional services for public works

Award: Competitive bid

The project team

HDR Engineering IncPrime Contractor
AECOM Technical Services IncSubcontractor$400,000
Next contract in this departmentTraining for the Public Utilities Commission350th of 493 active contracts in this department by amount agreed$599,900

Contract 1000028741 · Source: Supplier Contracts · every payment on this contract