Original title: “AIR-10504.77-AirTrainSysExtens”
$263,753
paid on this contract in FY2023
Paid to, since FY2018
Alstom Transport USA Incprime contractor$48.8MPaid from, FY2023
The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.
Airport fund · multi-year projects$263,753
Paid year by year, FY2018–FY2023
$1.2M in FY2018 · $25.9M in FY2022 (the highest) · $263,753 in FY2023
Click a year to see its amount.
Payment detail begins FY2018 ⓘ
Type and award
Contract type: Construction
Award: Competitive bid
The project team
Alstom Transport USA IncPrime Contractor
CMC Traffic Control Specialists LLCSubcontractor · LBE$569,300
Contract 1000004006 · Source: Supplier Contracts · every payment on this contract