Skip to main content

Municipal Transportation Agency

Professional services for Twin Peaks tunnel work

Original title: “CRCT1282R-TWIN PEAKS TUNNEL TR”

$7.6M
paid on this contract in FY2018
$7.6M paid since FY2018, of $33.0M on file as agreed since July 2017 · ended June 2022

Paid to, since FY2018

NTK Construction Incprime contractor$7.6M

Paid from, FY2018

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Muni transit fund · multi-year projects100%$7.6M

Type and award

Contract type: Professional services under the City Charter

Award: Competitive bid

Contract 1000005419 · Source: Supplier Contracts · every payment on this contract