Skip to main content
Qipu

Materials Tst Special Inspection Service PHSB

Smith Emery of San Francisco and Res Eng · DPW GSA - Public Works

San Francisco agreed $2.6M with Smith Emery of San Francisco and Res Eng for contract 1000009258 (DPW GSA - Public Works); $3.8M has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.

Register title:PW Mtrl Tst Spcl Insp Svc PHSB

Signed by GSA - Public Works

Agreed
$2.6M
Paid
$3.8M
more than the recorded base
Remaining (calculated)
$0
The money
Paid against the agreed amount

$3.8M paid · $1.2M more than the recorded base amount · Agreed $2.6M

Payments per fiscal year
20212223242526
Largest year: $657,545 · dashed = fiscal year not closed yet

These bars total $2.1M; the figure above is $3.8M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.

Payment detail begins FY2018
The deal
Contract term
September 5, 2018December 31, 2026
Term running
Recorded purchasing authority
Purchasing authority, verbatim
TERM CONTRACT PROFSERV-BID, ENVIRONMENTAL CONSULTING

See every contract awarded under Competitive bid →

Project team
SupplierRoleAttached $
Smith Emery of San Francisco and Res EngPrime
C M PROSLBESubcontractor$300,000
DABRI INCLBESubcontractor$100,000

Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.

Sources
This contract in the source
Raw rows (JSON, data.sfgov.org)