Skip to main content

Airport Commission

Wayfinding improvements at SFO

Original title: “AIR-11001.66Wayfinding Enhance”

$1.7M
paid on this contract in FY2023
$41.6M paid so far, of $41.9M agreed · ended December 2022

Paid to

Fisher Development Inc.prime contractor$41.6M

Paid from, FY2023

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Airport fund · multi-year projects100%$1.7M

Paid year by year, FY2018–FY2023

$433,129 in FY2018 · $16.3M in FY2022 (the highest) · $1.7M in FY2023

Click a year to see its amount.

Type and award

Contract type: Construction

Award: Competitive bid

The project team

Fisher Development, Inc.Prime Contractor
Rosendin Electric IncSubcontractor$311,472
George E Masker IncSubcontractor$42,181
Fisher Development, Inc.Subcontractor$24,755
Priority Architectural GraphicsSubcontractor · LBE$22,852
Lahue & AssociatesSubcontractor · LBE$16,504
Lloyd W. Aubry Company, IncSubcontractor$16,504
Associated Terrazo Company, Inc.Subcontractor · LBE$12,778
The 11 other team members
Galliera Inc DBA Trico ConstructionSubcontractor · LBE$12,313
Billings Jackson Design LLCSubcontractor$7,300
Chaves & AssociatesSubcontractor · LBE$7,300
City IDSubcontractor$7,300
Corgan Associates IncSubcontractor$7,300
Faith Group LLCSubcontractor$7,300
Hra Consulting EngineersSubcontractor · LBE$7,300
Olmm Consulting EngineersSubcontractor · LBE$7,300
Telamon Engineering Consultants IncSubcontractor · LBE$7,300
Liberty Electric of San Mateo IncSubcontractor · LBE$5,486
San Francisco Interiors, Inc.Subcontractor$3,867