Original title: “Electric AMI System (CS-1100)”
$1.1M
paid on this contract in FY2025
October 1, 2018September 30, 2028
Paid to
Aclara Technologies LLCprime contractor$2.9MPaid from, FY2025
The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.
Hetch Hetchy power fund$925,557
Hetch Hetchy power fund · multi-year projects$85,243
Hetch Hetchy power fund · annual projects$68,108
Paid year by year, FY2019–FY2026
$78,853 in FY2019 · $1.1M in FY2025 (the highest) · $122,171 in FY2026
Click a year to see its amount.
Type and award
Contract type: Purchases of goods and equipment
Award: Sole-source waiver
Contract 1000009594 · Source: Supplier Contracts · every payment on this contract