Skip to main content

Public Utilities Commission

Geothermal power and renewable energy credits from the Geysers

Original title: “PUC_CLP_GEYSER ENERGY+RECs”

$25.7M
paid on this contract in FY2025
$148.3M paid so far, of $243.0M agreed · runs to December 2029
May 1, 2018December 31, 2029
running

Paid to

Calpine Energy Services LPprime contractor$148.3M

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

CleanPowerSF fund · multi-year projects100%$25.7M

Paid year by year, FY2020–FY2026

$9.2M in FY2020 · $26.0M in FY2023 (the highest) · $24.9M in FY2026

Click a year to see its amount.

Type and award

Contract type: Rents and other non-purchase agreements

Award: Administrative Code 21.04(a)(6)-direct purchase by general manager of PUC

Next contract in this departmentLong-term energy contract for the Public Utilities Commission11th of 493 active contracts in this department by amount agreed$223.9M

Contract 1000010115 · Source: Supplier Contracts · every payment on this contract