Original title: “ASR - Property Tax System”
$460,781
paid on this contract in FY2025
November 1, 2018June 30, 2032
Paid to
Sapient Corporationprime contractor$21.5MPaid from, FY2025
The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.
General Fund · operating$460,781
Paid year by year, FY2019–FY2026
$919,344 in FY2019 · $4.9M in FY2021 (the highest) · $2.5M in FY2026
Click a year to see its amount.
Type and award
Contract type: Professional services
Award: Competitive bid
The project team
Sapient CorporationPrime ContractorFivepaths LLCSubcontractor · LBE$856,588
Contract 1000010122 · Source: Supplier Contracts · every payment on this contract