Skip to main content

Airport Commission

Airport work: As Needed A&E Support

Original title: “AIR-11372.50-AsNeededA&E Supp.” · prime is a certified Local Business Enterprise

$566,732
paid on this contract in FY2025
$2.2M paid so far, more than the $1.8M recorded as agreed · runs to May 2027
January 22, 2020May 19, 2027
running

Paid to

Paulett Taggart Architects Incprime contractor$2.2M

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Airport fund · multi-year projects62%$352,550
Airport fund38%$214,182

Paid year by year, FY2023–FY2026

$23,641 in FY2023 · $1.3M in FY2026

Click a year to see its amount.

Type and award

Contract type: Professional services for public works

Award: Competitive bid

The project team

Paulett Taggart Architects IncPrime Contractor · LBE
FW Associates IncSubcontractor · LBE$210,000
SJ EngineersSubcontractor · LBE$210,000
Rivera Consulting Group IncSubcontractor · LBE$195,000
Studio BanaaSubcontractor · LBE$90,000
Charles M Salter Associates IncSubcontractor$60,000
JS Nolan & Assoc Lighting Design LLCSubcontractor · LBE$60,000
Lowercase Productions, LLCSubcontractor · LBE$60,000
The 9 other team members
M Lee CorporationSubcontractor · LBE$60,000
Stok LLCSubcontractor$60,000
Emily Borland Specifications IncSubcontractor · LBE$50,100
FTF Engineering IncSubcontractor · LBE$45,000
Cal AccessibilitySubcontractor$30,000
Fletcher StudioSubcontractor · LBE$30,000
Luk and AssociatesSubcontractor$15,000
Rockridge Geotechnical IncSubcontractor$15,000
Bruce Damonte Photography IncSubcontractor$9,900
Next contract in this departmentAirport work: As-Needed Elect114th of 294 active contracts in this department by amount agreed$1.8M

Contract 1000016939 · Source: Supplier Contracts · every payment on this contract