Skip to main content

Public Utilities Commission

Stormwater billing project for the Public Utilities Commission

Original title: “Stormwater Billing Project”

$3.7M
paid on this contract in FY2024
$3.7M paid so far, of $3.7M agreed · runs to June 2027
July 1, 2020June 30, 2027
running

Paid to

Langan Engineering & Environmental Servprime contractor$3.7M

Paid from, FY2024

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Wastewater fund83%$3.1M
Public Utilities Commission fund · operating17%$623,052

Type and award

Contract type: Purchases of goods and equipment

Award: Competitive bid

Next contract in this departmentAs-needed general engineering work for the Public Utilities Commission205th of 493 active contracts in this department by amount agreed$3.7M

Contract 1000017310 · Source: Supplier Contracts · every payment on this contract