11656.71-CMGCAirfieldImprv

GOLDEN GATE CONSTRUCTORS · AIR Airport Commission

San Francisco agreed $267.7M with GOLDEN GATE CONSTRUCTORS for contract 1000018689 (AIR Airport Commission); $259.7M has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.

Register title:AIR-11656.71-CMGCAirfieldImprv

Signed by Airport Commission

Agreed
$267.7M
Paid
$259.7M
97% of agreed
Remaining (calculated)
$7.9M
The money
Paid against the agreed amount
Payments per fiscal year
2122232425
Largest year: $100.9M
Payment detail begins FY2018
The deal
Contract term
August 18, 2020September 1, 2025
Term ended
Recorded purchasing authority
Purchasing authority, verbatim
AIRPORT COMMISSION AUTHORITY - DOCUMENT BID

See every contract awarded under Competitive bid →

Project team
SupplierRoleAttached $
GOLDEN GATE CONSTRUCTORSPrime
ORION ENGINEERS AND ASSOCIATESSubcontractor$1.4M
HOLLINS CONSULTING INCLBESubcontractor$200,000
ROYAL ELECTRIC COSubcontractor$200,000