Public Utilities Commission

Hetch Hetchy Power electricity scheduling contract

Original title: “PUC_HHP_CAISO” · nonprofit contractor

$54,163
paid on this contract in FY2024
$385,621 paid so far, of $5.0M agreed · runs to June 2050
August 4, 2021June 30, 2050
running

Paid to

California Isoprime contractor$385,621

Paid from, FY2024

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

CleanPowerSF fund · multi-year projects100%$54,163

Paid year by year, FY2022–FY2026

$283,015 in FY2022 · $48,443 in FY2026

Click a year to see its amount.

Type and award

Contract type: Rents and other non-purchase agreements

Award: Administrative Code 21.04(a)(6)-direct purchase by general manager of PUC