Original title: “TC71619 PUC Sunol Auto Parts”
$7,126
paid on this contract in FY2025
February 1, 2022January 31, 2027
Contractor
Napa Auto Parts
Paid from, FY2025
The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.
Water fund · operating$7,126
Paid year by year, FY2022–FY2026
$9,732 in FY2022 · $30,828 in FY2023 (the highest) · $25,700 in FY2026
Click a year to see its amount.
Type and award
Contract type: Goods bought on contracts for a set period
Award: Competitive bid
Contract 1000024010 · Source: Supplier Contracts · every payment on this contract