Original title: “AIR50294 - LAB ANALYSIS”
$916
paid on this contract in FY2025
January 1, 2022December 31, 2026
Contractor
La Testing
Paid from, FY2025
The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.
Airport fund · operating$916
Paid year by year, FY2023–FY2026
$285 in FY2023 · $916 in FY2025 (the highest) · $499 in FY2026
Click a year to see its amount.
Type and award
Contract type: Professional services under the City Charter
Award: Competitive bid
Contract 1000024459 · Source: Supplier Contracts · every payment on this contract