AN Project Control & CM 2 (MLBE)

InnoActive Group, LLC · DPW GSA - Public Works

San Francisco agreed $825,000 with InnoActive Group, LLC for contract 1000024503 (DPW GSA - Public Works); $0 has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.

Register title:PW AN Proj Ctrl & CM 2 (MLBE)

Signed by GSA - Public Works

LBE
Agreed
$825,000
Paid
$0
0% of agreed
Remaining (calculated)
$825,000
The money
Paid against the agreed amount
Payments per fiscal year

No voucher-level payment detail for this contract (detail begins FY2018 — earlier or indirect payments don’t appear).

Payment detail begins FY2018
The deal
Contract term
March 16, 2022April 3, 2027
Term running
Recorded purchasing authority
Purchasing authority, verbatim
TERM CONTRACT PROFSERV-BID, ENVIRONMENTAL CONSULTING

See every contract awarded under Competitive bid →

Project team
SupplierRoleAttached $
InnoActive Group, LLCLBEPrime
InnoActive Group, LLCSubcontractor$825,000
CUMMING MANAGEMENT GROUP, INCSubcontractor$750,000
CM SolutionsSubcontractor$450,000
CHAVES & ASSOCIATESLBESubcontractor$150,000

Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.