Original title: “Contract”
$200,155
paid on this contract in FY2025
November 1, 2022October 31, 2026
Paid to
Hollins Consulting Incprime contractor$1.0MPaid from, FY2025
The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.
Port fund · multi-year projects$200,155
Paid year by year, FY2023–FY2026
$338,292 in FY2023 · $377,486 in FY2024 (the highest) · $75,338 in FY2026
Click a year to see its amount.
Type and award
Contract type: Professional services for public works
Award: Competitive bid
The project team
Hollins Consulting IncPrime ContractorSustainable Watershed Designs IncSubcontractor · LBE$900,000
Vara Land SurveyingSubcontractor · LBE$210,000
Edgar Lopez & Associates, LLCSubcontractor · LBE$90,000
Contract 1000025032 · Source: Supplier Contracts · every payment on this contract