Skip to main content

Public Utilities Commission

As-needed tree work for the Public Utilities Commission

Original title: “PUC Master As-Needed Tree Srvs”

$525,300
paid on this contract in FY2025
$1.9M paid so far, more than the $1.4M recorded as agreed · runs to January 2028
April 12, 2022January 17, 2028
running

Paid to

West Coast Arborists Incprime contractor$1.9M

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Water fund · operating57%$297,450
Water fund · annual projects43%$227,850

Paid year by year, FY2024–FY2026

$158,050 in FY2024 · $1.2M in FY2026

Click a year to see its amount.

Type and award

Contract type: Construction marked “unilateral”

Award: Competitive bid

The project team

West Coast Arborists IncPrime Contractor
Bay Area Arborist Cooperative IncSubcontractor · LBE$1.4M
Next contract in this departmentAs-needed energy engineering services, Public Utilities Commission291st of 493 active contracts in this department by amount agreed$1.3M

Contract 1000025060 · Source: Supplier Contracts · every payment on this contract