Skip to main content

Public Utilities Commission

Power distribution for the Mission Rock redevelopment

Original title: “PUC_HHP_MISSIONROCKREDEVELOPME”

$46,337
paid on this contract in FY2025
$608,877 paid so far, of $750,000 agreed · runs to June 2032
June 7, 2022June 6, 2032
running

Paid to

Mission Rock Horizontal Sub (Phase 1)LLCprime contractor$608,877

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Hetch Hetchy power fund100%$46,337

Paid year by year, FY2023–FY2025

$371,633 in FY2023 · $46,337 in FY2025

Click a year to see its amount.

Type and award

Contract type: Rents and other non-purchase agreements

Award: Contracting with Developers to Install Electric Facilities at New Developments

Next contract in this departmentMeter reading software and services for Public Utilities Commission334th of 493 active contracts in this department by amount agreed$750,000

Contract 1000026472 · Source: Supplier Contracts · every payment on this contract