Skip to main content

Public Utilities Commission

New campus for the water utility's city distribution division

Original title: “PUC CDD Campus at 2000 Marin”

$12.1M
paid on this contract in FY2025
$155.7M paid so far, of $305.8M agreed · runs to November 2029
December 6, 2022November 27, 2029
running

Paid to

Clark Construction Group - California LPprime contractor$155.7M

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Water fund · multi-year projects95%$11.5M
Water fund5%$657,845

Paid year by year, FY2023–FY2026

$110,500 in FY2023 · $123.1M in FY2026

Click a year to see its amount.

Type and award

Contract type: Construction marked “unilateral”

Award: Competitive bid

Next contract in this departmentRenewable electricity for CleanPowerSF6th of 493 active contracts in this department by amount agreed$301.3M

Contract 1000027086 · Source: Supplier Contracts · every payment on this contract