Skip to main content
Qipu

Sewp Control HVAC & Mac Upgrade

CAL STATE CONSTRUCTORS INC · PUC Public Utilities Commsn

San Francisco agreed $6.1M with CAL STATE CONSTRUCTORS INC for contract 1000027489 (PUC Public Utilities Commsn); $23.2M has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.

Register title:PUC SEWP CTRL HVAC & MAC UPGRD

Signed by Public Utilities Commsn

Agreed
$6.1M
Paid
$23.2M
more than the recorded base
Remaining (calculated)
$0
The money
Paid against the agreed amount

$23.2M paid · $17.1M more than the recorded base amount · Agreed $6.1M

Payments per fiscal year
23242526
Largest year: $4.9M · dashed = fiscal year not closed yet

These bars total $11.6M; the figure above is $23.2M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.

Payment detail begins FY2018
The deal
Contract term
November 7, 2022October 9, 2026
Term running
Recorded purchasing authority
Purchasing authority, verbatim
CONSTRUCTION SERVICES

See every contract awarded under Competitive bid →

Project team
SupplierRoleAttached $
CAL STATE CONSTRUCTORS INCPrime
BLOCKA CONSTRUCTION INCSubcontractor$5.3M
BAYTECH ENGINEERING, INC.LBESubcontractor$1.0M
E MITCHELL INCLBESubcontractor$832,210
ANDERSON ROOFING & SHEET METAL CO INCLBESubcontractor$554,255
UNION DOORLBESubcontractor$318,208
REDWOOD PAINTING CO INCSubcontractor$41,400

Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.