Generator Maintenance

Original title: “TC77101C Generator Maintenance”

$35,936
paid on this contract in FY2025
$42,991 paid so far, of $900,000 agreed · runs to August 2027
August 4, 2023August 3, 2027
running

Paid to

Edward R Bacon Co Incprime contractor$42,991

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

General Fund · multi-year projects100%$35,936

Paid year by year, FY2024–FY2025

FY2025$35,936
FY2024$7,055

Type and award

Contract type: Services bought on contracts for a set period

Award: Competitive bid

Next contract in this departmentGenerator Maintenance455th of 826 active contracts in this department by amount agreed$900,000