Historic Resources Analysi
PAGE & TURNBULL INC · CPC City Planning
San Francisco agreed $800,000 with PAGE & TURNBULL INC for contract 1000028133 (CPC City Planning); $334,698 has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.
Register title: “CPC Historic Resources Analysi”
Signed by City Planning
These bars total $785,785; the figure above is $334,698. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
| Supplier | Role | Attached $ |
|---|---|---|
| PAGE & TURNBULL INC | Prime | — |
| Edutainment for EquityLBE | Subcontractor | $400,000 |
| INCOMMON LLCLBE | Subcontractor | $400,000 |
| VERPLANCK HISTORIC PRESERVATION CONSLTNGLBE | Subcontractor | $400,000 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)