Puc Plant Management-Alameda

ARBORIST NOW INC · ADM GSA - City Administrator

Puc Plant Management-Alameda, bought on term contract 75220D. Term contracts are standing arrangements: departments order against them over the contract period rather than buying once. San Francisco agreed $2.8M with ARBORIST NOW INC for contract 1000028779 (ADM GSA - City Administrator); $1.3M has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.

In plain English

Puc Plant Management-Alameda, bought on term contract 75220D. Term contracts are standing arrangements: departments order against them over the contract period rather than buying once.

Register title:TC75220D PUC PLANT MGT-ALAMEDA

Signed by GSA - City Administrator

LBE
Agreed
$2.8M
Paid
$1.3M
47% of agreed
Remaining (calculated)
$1.5M
The money
Paid against the agreed amount
Payments per fiscal year
24252627
Largest year: $553,353 · dashed = fiscal year not closed yet

These bars total $1.5M; the figure above is $1.3M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.

Payment detail begins FY2018
The deal
Contract term
May 15, 2023May 14, 2028
Term running
Recorded purchasing authority
Purchasing authority, verbatim
COMPETITIVE SOLICITATION

See every contract awarded under Competitive bid →

Project team
SupplierRoleAttached $
ARBORIST NOW INCLBEPrime
KOROTKIN ASSOCIATES INCLBESubcontractor$310,000

Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.

Sources
This contract in the source