Skip to main content
Qipu

job order contract-93 General Engineering (A-Licen)

M HERNANDEZ CONSTRN DBA HERNANDEZ ENGRNG · PUC Public Utilities Commsn

San Francisco agreed $6.0M with M HERNANDEZ CONSTRN DBA HERNANDEZ ENGRNG for contract 1000028865 (PUC Public Utilities Commsn); $1.5M has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.

Register title:PUC JOC-93 Gnrl Engi (A-Licen)

Signed by Public Utilities Commsn

LBE
Agreed
$6.0M
Paid
$1.5M
24% of agreed
Remaining (calculated)
$4.5M
The money
Paid against the agreed amount
Payments per fiscal year
242526
Largest year: $2.5M · dashed = fiscal year not closed yet

These bars total $2.6M; the figure above is $1.5M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.

Payment detail begins FY2018
The deal
Contract term
May 3, 2023May 2, 2028
Term running
Recorded purchasing authority
Purchasing authority, verbatim
CONSTRUCTION SERVICES

See every contract awarded under Competitive bid →

Project team
SupplierRoleAttached $
M HERNANDEZ CONSTRN DBA HERNANDEZ ENGRNGLBEPrime
GSW Construction Inc.LBESubcontractor$452,780
ARBORIST NOW INCLBESubcontractor$447,220
BAYTECH ENGINEERING, INC.LBESubcontractor$300,000
PUMP REPAIR SERVICE CO INCSubcontractor$150,000
WATERTIGHT RESTORATION INCLBESubcontractor$150,000
NETRONIX INTEGRATIONSubcontractor$0
ROADRUNNER DRILLING & PUMP COMPANY INCSubcontractor$0
+ 1 more on the team
UNDERWATER RESOURCES INCSubcontractor$0

Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.

Sources
This contract in the source
Raw rows (JSON, data.sfgov.org)