Skip to main content

Airport Commission

Financial capital plan analysis for the Airport

Original title: “AIR50283.02 FinCapPlanAnalysis”

$170,143
paid on this contract in FY2025
$179,253 paid so far, of $420,000 agreed · runs to June 2028
July 1, 2023June 30, 2028
running

Contractor

Robert Kuo Consulting LLC

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Airport fund · operating100%$170,143

Paid year by year, FY2024–FY2025

FY2025$170,143
FY2024$9,110

Type and award

Contract type: Professional services under the City Charter

Award: Competitive bid

The project team

Robert Kuo Consulting LLCPrime Contractor
Avk Consulting IncSubcontractor$360,000
Landrum & Brown IncorporatedSubcontractor$360,000
Capital Partnerships IncSubcontractor · LBE$60,000
Next contract in this departmentProfessional services for the Airport169th of 294 active contracts in this department by amount agreed$414,175

Contract 1000029009 · Source: Supplier Contracts · every payment on this contract