Original title: “AIR-11800.52-As-Needed Agreeme”
$902,046
paid on this contract in FY2025
July 10, 2023July 10, 2028
Paid to
PGH Wong-Avila JVprime contractor$1.7MPaid from, FY2025
The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.
Airport fund$886,038
Airport fund · multi-year projects$16,008
Paid year by year, FY2024–FY2026
$214,815 in FY2024 · $902,046 in FY2025 (the highest) · $488,420 in FY2026
Click a year to see its amount.
Type and award
Contract type: Professional services for public works
Award: Competitive bid
The project team
PGH Wong-Avila JVPrime ContractorAvila & Assoc Consulting Engineers IncJoint Venture Constituent$0
PGH Wong Engineering IncJoint Venture Constituent$0
PGH Wong Engineering IncSubcontractor$1.0M
Avila & Assoc Consulting Engineers IncSubcontractor · LBE$787,334
Saylor Consulting GroupSubcontractor$496,800
PMCM2Subcontractor · LBE$425,000
Studio 151Subcontractor · LBE$363,657
The 9 other team members
Chaves & AssociatesSubcontractor · LBE$160,000
Landrum & Brown IncorporatedSubcontractor$160,000
M Lee CorporationSubcontractor · LBE$120,000
Ross & Baruzzini IncSubcontractor$120,000
OrgMetrics LLCSubcontractor$80,000
Pro-Tec Safety Consultants Inc.Subcontractor · LBE$80,000
Amc Consulting Engineers IncSubcontractor · LBE$60,260
ECSSubcontractor$60,000
Logplan, IncSubcontractor$40,000
Contract 1000029073 · Source: Supplier Contracts · every payment on this contract