Surveying service no. 6

Original title: “PW AN Srvyng Svc No. 6”

$1.1M
paid on this contract in FY2025
$2.5M paid so far, more than the $2.5M recorded as agreed · runs to February 2029
December 15, 2023February 7, 2029
running

Paid to

Chaudhary & Assoc Incprime contractor$2.5M

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. A special revenue fund holds money earmarked for a purpose, often grants. The fund does not say where the money first came from.

Capital projects fund · multi-year projects39%$410,149
Special revenue fund · multi-year projects38%$398,760
Port fund · multi-year projects16%$174,282
Sustainable Streets fund · multi-year projects4%$39,988
Sustainable Streets fund3%$33,547

Paid year by year, FY2024–FY2026

$215,075 in FY2024 · $1.1M in FY2025 (the highest) · $931,688 in FY2026

Click a year to see its amount.

Type and award

Contract type: Professional services for public works

Award: Competitive bid

The project team

Chaudhary & Assoc IncPrime Contractor
Pacific Engineering & Construction IncSubcontractor · LBE$540,000
Vertical Mapping ResourcesSubcontractor · LBE$0
Next contract in this departmentConstruction for a transit improvement project96th of 282 active contracts in this department by amount agreed$2.4M