As-Needed ProjectMngntSrvs
LEE INCORPORATED · PUC Public Utilities Commsn
San Francisco agreed $3.0M with LEE INCORPORATED for contract 1000031693 (PUC Public Utilities Commsn); $1.1M has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.
Register title: “PUC As-Needed ProjectMngntSrvs”
Signed by Public Utilities Commsn
These bars total $1.2M; the figure above is $1.1M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
| Supplier | Role | Attached $ |
|---|---|---|
| LEE INCORPORATED | Prime | — |
| SRT CONSULTANTSLBE | Subcontractor | $950,000 |
| MCGOVERN MCDONALD ENGINEERSLBE | Subcontractor | $475,000 |
| CHAVES & ASSOCIATESLBE | Subcontractor | $332,500 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.