Public Utilities Commission

As-needed fire protection work for the Public Utilities Commission

Original title: “PUC MST As-Needed Fire Protect”

$3,426
paid on this contract in FY2025
$121,873 paid so far, of $750,000 agreed · runs to November 2028
November 27, 2023November 26, 2028
running

Paid to

Siemens Industry Incprime contractor$121,873

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Wastewater fund · operating74%$2,546
Water fund · operating26%$880

Paid year by year, FY2025–FY2026

FY2026$118,447
FY2025$3,426

Type and award

Contract type: Construction marked “unilateral”

Award: Competitive bid

Next contract in this departmentAs-needed fire protection work for the Public Utilities Commission337th of 493 active contracts in this department by amount agreed$750,000

Contract 1000031698 · Source: Supplier Contracts · every payment on this contract