Airport construction: As-Needed Envir

Original title: “AIR- 12020.53-As-Needed Envir”

$84,400
paid on this contract in FY2025
$506,340 paid so far, of $2.2M agreed · runs to February 2029
February 28, 2024February 27, 2029
running

Paid to

Pacific States Environmental Contractorsprime contractor$506,340

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Airport fund · multi-year projects100%$84,400

Paid year by year, FY2025–FY2026

FY2026$421,940
FY2025$84,400

Type and award

Contract type: Construction

Award: Competitive bid

The project team

Pacific States Environmental ContractorsPrime Contractor
KM 106 Construction Inc.Subcontractor · LBE$61,000
Next contract in this departmentAirport work: As-Needed EEWCS105th of 294 active contracts in this department by amount agreed$2.1M